In BAPI_PO_CREATE1 there are various tables like POITEM, POITEMX.... I wanted to know what is the purpose of the second table(POITEMX)...the documentation says its for the fields which have changed. Can anyone kindly explain.FUNCTION Z_BC1_BAPI_PO_CR

View All Replies

BAPI_PO_CREATE1 for blocked item and account assignment category Q

October 11

Hi, I am facing an issue while creating PO with items which are blocked ie LOEKZ = 'S', and account assignment category 'Q'. Though I fill wbs element in POACCOUNT and POACCOUNTX structures, after execution it is being erased and am getting an error:

View All Replies

WBS - Error in Expected Costs after Service Receipt

November 30

Hi to all, we are working with SRM Server 4, sp9 using Extended Classic Scenario. We've created a "PO ref. to contracts" and we've assigned costs to WBS budget. All works fine because total value of PO has been added to "Commitment Line&quo

View All Replies

Problem opening Project/WBS Elements in CJ03

October 11

Hi Experts, I have created an interface which posts PROJECT01 Idocs into SAP 6.0. Idocs are posted successfully and I can see Projects/WBS elements in tables PROJ and PRPS. However, when I try to open a project/wbs through transaction CJ03, it throws

View All Replies

Migration of PO with "free item" indicator not working (BAPI_PO_CREATE1)

October 11

Hi experts, we are using the BAPI_PO_CREATE1 to migrate POs. However, when we try to create a line item with a price of 0.0  and a "free item" indicator, the PO is created with a price and without the "free item" indicator (price seems

View All Replies

How to uploading multiple WBS from xls

November 30

Dear X'perts, Can anyone direct me how to upload multiple WBS from an xls file, say if I want to upload more than 500 WBS at once? rgds M THi Mazal, As already answered by kusam avinash that you can use LSMW and use the T code CJ11 for the same. Plea

View All Replies

Change of Account Assignment (WBS) in Sales Order

October 11

While crteating a sales order w.r.t. quotation, account assignment is automatically made with the WBS mentioned earlier in the quotation, which is showing grey (disable). But what is the procedure for changing the WBS in the sales order.Hi, Go to XD9

View All Replies

Wbs cannot be deleted

November 30

what are the instances why wbs cannot be deleted? what to do if wbs for deletion has incurred actual costs?In such a case you have to lock the WBS, so that no further postings happens on the same or else set the deletion flag on WBS. SarangRead other

View All Replies

How to find out System Status of WBS Elements?

October 11

Hi PS Experts! Please help me on my query. I want to get a list of WBS elements whose status is Released and can be used. If I try to search the table PRPS, it can only help me in finding WBS elements without deletion flag, with RA Key and so on. But

View All Replies

Report PS to check by WBS group

November 30

Hi All, Can we use WBS group rather than project definition in SAP PS report ? I am trying to find the standard report to use WBS group...but cannot find..... please help. cheers, NiesI've used WBS groups for allocations/periodic reposting and planni

View All Replies

BAPI_PO_CREATE1 Prcicing Conditions

November 30

Hi,      By using BAPI_PO_CREATE1 i can create Purchase orders successfully i am trying to update with pricing condtions by using this function module. Pricing details  are maintained in Purchase order.But the problem same pricing condition is append

View All Replies

Downpayment..milestone..periodic billing...WBS element...

November 30

downpayment..milestone billing.....periodic billing...WBS element...billing plan..commission agent....rentals...extra work in construction...cancellation of flat..allotment of parking..sale of real estate unit..sale of TDR..sale of services...payment

View All Replies

How to post overhead costs in WBS object currency?

November 30

I have a requirement to post the overhead costs (t.code CJ45) to the WBS elements in the respective WBS element object currency instead of the controlling area currency or the company code currency. How can i configure this?AnsweredRead other 2 answe

View All Replies

Find table with wbs element list

November 30

Hi experts, i have the wbs element id number (i found it from a function) but i dont know how can i find the wbs element description table. any help will be appreciated. Michal.i found it, thanks. Michal.Read other 2 answers

View All Replies

Need WBS split to AUC and Expanses during settlement (not %wise)

November 30

Hi, We have some capital projects settling to AUC but we are also charging WBS for labor costs and travel expanses and offcouse capital costs. Managment wants PS team to Settle labor/travel to CCTR and Capital cost to AUC. How can WBS recognize cost

View All Replies

IDOC WBS

November 30

Dear, I want to use Idoc- WBS to do inbound/outbound operation (SAP -> XML and vice-versa) I am not able to find the Message type use for WBS, but tried with Project/Project01, system displayed message that Project is use for BAPI. So, finally unable

View All Replies

Report Painter Request - Cost Center and WBS Element

October 11

Hi Everyone, Currently, my company settles all project related expenses through to a cost center by way of an internal settlement cost element (category 21).  The issue with this is that when the expense gets to the cost center, they lose all visabil

View All Replies

Changing WBS element in PO

November 30

Hi In my Purchase Order, earlier it was account assigned to a WBS element A. When we ran CJI3, it showed the same. But now the account assignment of WBS element was changed to B. I have no idea how this got changed. I only can check from the Purchase

View All Replies

SAP PS: Changing the WBS number for a released project

November 30

Hi Gurus, I am wondering if anyone here knows how to change the WBS number under a project that is released (REL). Until the project is partially released (PREL), the WBS number can be changed, but once it's released, the number is greyed out. Is the

View All Replies

Upload of Cwip  WBS wise

November 30

Hello, in my organisation, FI is active but PS not yet active. Now till date we are posting all the CWIP related entries to manual CWIP account with a reference to WBS Element. WBS are already created. Now, we want to make PS live. My question is: Ca